CS615-Midterm
1 / 50
The process of ensuring that the project is running in the right direction is called .
2 / 50
Project management is a _________of constant communication and negotiation.
3 / 50
________ theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins. Select correct option
4 / 50
includes the processes required to ensure that the project is completed within the approved budget
5 / 50
A ‘facilitator’ controls the meeting can be _________.
6 / 50
To ________risks from occurring, the project team prepares the risk plan before the commencement of the project.
7 / 50
Which of the following is a Technology related problem?
8 / 50
The fourth, and current, phase of software solution began in the early
9 / 50
Which along with CMM (capability maturity model) helps in creating effective software process model for any organization?
10 / 50
Implementing software quality is often associated with the .
11 / 50
The model serves as a foundation for software
12 / 50
Software requirements engineering is a process of all except
13 / 50
Project management processes can be organized into groups?
14 / 50
A software project that meets all the stated objectives is a success of
15 / 50
Cognitive model describes a system as perceived by its _________.
16 / 50
McCall (MCC77) and his colleagues proposed some software quality factors based on _________ most important aspects of a software product:
17 / 50
According to the 80/20 rule, 80 percent of the defects arise due to of the process issues.
18 / 50
Predecessor activities need to ________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. Select correct option:
19 / 50
A good system allows you to access relevant information and make informed decisions.
20 / 50
Cognitive model describes a system as perceived by its _________
21 / 50
These all are Product Revision Factors except.
22 / 50
Which of the following is not desirable to become a successful project manager?
23 / 50
Software project are carried out sequentially and that each phase is completed before the next is taken up.
24 / 50
Which of the following might require re-baselining of the cost baseline?
25 / 50
Product quality depends on its conformance to ______
26 / 50
27 / 50
Project management processes can be organized into _____________ groups
28 / 50
________ is path finding________, is path following
29 / 50
During the Implementation phase the software modules are coded and initial unit tests are performed.
30 / 50
Most software project manager’s practice a lot of management techniques that are of doubtful authenticity are called
31 / 50
The British Standards Institution(1986) has stated the quality as
32 / 50
Tools and techniques of the source selection process include all of the following except
33 / 50
Software design is actually a multi-step process that focuses on distinct attributes of a program
34 / 50
The Efficiency with which a program runs on different platforms or operating systems is called :
35 / 50
Using PERT and CPM, ________ , helps you complete a project on time. By using these techniques, you can determine the latest time by when an activity should start to be completed on time.
36 / 50
The Introduction of the software requirements specification states the
37 / 50
To manage costs for software projects, you need an accurate estimation of costs. To do that, there is a sequence of steps that you need to perform, mark first step in sequence to perform.
38 / 50
_______is the technical kernel of software engineering
39 / 50
McCall (MCC77) and his colleagues proposed some software quality factors based on most important aspects of a software product:
40 / 50
During the period of , you will find that software that was produced was generally over budgeted, under scheduled, and of poor quality.
41 / 50
________ is a software engineering task that bridges the gap between system level requirements engineering and software design.
42 / 50
Controlling Versions is activity of
43 / 50
Which organization has set the de facto standards for project management techniques?
44 / 50
only one is the output of Initiating Process
45 / 50
is an umbrella activity that ensures conformance to standards and procedures throughout the SDLC of a software product.
46 / 50
Software design is actually a multi-step process that focuses, on distinct attributes of a program.
47 / 50
Identify the category of people who do actual work on software development.
48 / 50
These all are Product Operation Factors except
49 / 50
identifying and documenting interactivity dependencies
50 / 50
Over the course of the project, a comparison of the due date and the date delivered provides a metric for how well deliverable dates are ________ by the project team. Select correct option:
Your score is
The average score is 0%
Restart quiz