CS615-Midterm
1 / 50
Large corporations realized the benefits of using computers in .
2 / 50
The model serves as a foundation for software
3 / 50
These all are design phase activities except
4 / 50
Low motivation is a____ related problem.
5 / 50
Foundational design concepts are.
6 / 50
You can use the Item Traceability Matrix to identify _______ at the end of each phase
7 / 50
Each ________ can be subdivided into sub tasks.
8 / 50
These all are Product Operation Factors except
9 / 50
The model serves as the basis for the creation of ________ for the Software.
10 / 50
Cognitive model describes a system as perceived by its _________
11 / 50
McCall (MCC77) and his colleagues proposed some software quality factors based on most important aspects of a software product:
12 / 50
— ensures that appropriate steps to follow the product development procedures are carried out
13 / 50
14 / 50
To ________risks from occurring, the project team prepares the risk plan before the commencement of the project.
15 / 50
Implementing software quality is often associated with the .
16 / 50
________ is a software engineering task that bridges the gap between system level requirements engineering and software design.
17 / 50
To control versions, you can use _________.
18 / 50
Which of the following is not desirable to become a successful project manager?
19 / 50
To manage costs for software projects, you need an accurate estimation of costs. To do that, there is a sequence of steps that you need to perform, mark first step in sequence to perform.
20 / 50
A node on a network schedule is that point in time at which an activity ________.
21 / 50
These all are outputs of Initiating Process except
22 / 50
23 / 50
Project management processes can be organized into _____________ groups
24 / 50
A ‘facilitator’ controls the meeting can be _________.
25 / 50
26 / 50
During the Implementation phase the software modules are coded and initial unit tests are performed.
27 / 50
Which of the following might require re-baselining of the cost baseline?
28 / 50
A software project that meets all the stated objectives is a success of _________
29 / 50
Identify the category of people who do actual work on software development.
30 / 50
Upon evaluating current problems and desired information (input and output), the analyst begins to _________.
31 / 50
McCall (MCC77 )and his colleagues proposed some software quality factors based on most important aspects of a software product:
32 / 50
Most software project manager’s practice a lot of management techniques that are of doubtful authenticity are called
33 / 50
In understanding the organizations focusing symbols and meaning related to events. Culture is also important. It is fall under .
34 / 50
Decisions also have a--------------------element to them-the “right” decision may not be the "best' decision if it is made too early or too late.
35 / 50
Thy quality of software is said to be high if it meets the
36 / 50
The final activity for a project manager is
37 / 50
Predecessor activities need to ________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. Select correct option:
38 / 50
Efficiency with which a program runs on different platforms or operating systems is Reusability
39 / 50
________ identifying which quality standards are relevant to the project and determining how to satisfy them.
40 / 50
41 / 50
Tools and techniques of the source selection process include all of the following except
42 / 50
Auditing is activity of
43 / 50
Defined scope is a
44 / 50
Project management processes can be organized into groups?
45 / 50
What limits the options of the project team?
46 / 50
When you build a product or system, it’s important to go through a series of predictable steps – a road map that helps you create a timely, high-quality result, The road map that you follow is called —
47 / 50
only one is the output of Initiating Process
48 / 50
A meeting is conducted at a _________ and attended by both software engineers and customers.
49 / 50
________ theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins. Select correct option
50 / 50
Cognitive model describes a system as perceived by its _________.
Your score is
The average score is 0%
Restart quiz