CS615 Midterm Online Quiz

0%

CS615-Midterm

1 / 50

only one is the output of Initiating Process

2 / 50

A software project that meets all the stated objectives is a success of _________

3 / 50

The model serves as the basis for the creation of ________ for the Software.

4 / 50

Software design is actually a multi-step process that focuses on distinct attributes of a program

5 / 50

Predecessor activities need to ________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. Select correct option:

6 / 50

________ is a software engineering task that bridges the gap between system level requirements engineering and software design.

7 / 50

Cognitive model describes a system as perceived by its _________

8 / 50

The fourth, and current, phase of software solution began in the early

9 / 50

In understanding the organizations focusing symbols and meaning related to events. Culture is also important. It is fall under .

10 / 50

includes consideration such as the post-implementation support activities provided to the customer.

11 / 50

Project management processes can be organized into _____________ groups

12 / 50

The Introduction of the software requirements specification states the

13 / 50

Cognitive model describes a system as perceived by its _________.

14 / 50

—defining and refining objectives and selecting the best of the alternative courses of action to attain the objectives that the project was undertaken to address

15 / 50

Defined scope is a

16 / 50

________ is path finding________, is path following

17 / 50

A baseline version __________

18 / 50

Synchronization control helps to ensure that parallel changes performed by two different people do .

19 / 50

________________ managing the relationship with the seller.

20 / 50

The model serves as the basis for the creation of ________ for the Software.

21 / 50

In problem evaluation area of effort, once problems have been identified, the determines what information is to be produced by the new system and what data will be provided to the system.

22 / 50

Which of the following is a Technology related problem?

23 / 50

Configuration control tools include

24 / 50

These all are Product Revision Factors except

25 / 50

The fourth, and current, phase of software solution began in the early

26 / 50

A node on a network schedule is that point in time at which an activity ________.

27 / 50

Which of the following is not desirable to become a successful project manager?

28 / 50

A meeting is conducted at a _________ and attended by both software engineers and customers.

29 / 50

The model serves as a foundation for software

30 / 50

The first activity in risk analysis is risk management.

31 / 50

A good system allows you to access relevant information and make informed decisions.

32 / 50

We can classify the problems that affect software projects into categories

33 / 50

In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.

34 / 50

Cognitive model describes a system as perceived by its _________

35 / 50

_______is the technical kernel of software engineering

36 / 50

Foundational design concepts are.

37 / 50

Efficiency with which a program runs on different platforms or operating systems is Reusability

38 / 50

Defined scope is a

39 / 50

________ theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins. Select correct option

40 / 50

These all are outputs of Initiating Process except

41 / 50

Project management processes can be organized into groups?

42 / 50

These all are Product Operation Factors except

43 / 50

The US DOD (1988) defines software quality rather simply as

44 / 50

You can use the Item Traceability Matrix to identify _______ at the end of each phase

45 / 50

Low motivation is a____ related problem.

46 / 50

These all are Product Revision Factors except.

47 / 50

Software design is actually a multi-step process that focuses, on distinct attributes of a program.

48 / 50

These all are design phase activities except

49 / 50

Project management is a _________of constant communication and negotiation.

50 / 50

The British Standards Institution (1986) has stated the quality as

Your score is

The average score is 0%

0%

Qunoot e Nazilah
Dua e Hajat
4 Qul
6 Kalma
Dua-e-Akasha
Darood Akbar
Surah Fatiha
Dua-e-Ganj Ul Arsh
Dua-e-Jamilah
Ayat-ul-Kursi