CS615-Midterm
1 / 50
Each process is described by .
2 / 50
We can classify the problems that affect software projects into categories
3 / 50
The model serves as a foundation for software
4 / 50
Synchronization control helps to ensure that parallel changes performed by two different people do .
5 / 50
Configuration control tools include
6 / 50
A meeting is conducted at a _________ and attended by both software engineers and customers.
7 / 50
Mode of specification has a great impact on quality of solution. Forcing SWE to work with incomplete, inconsistence, or misleading specifications result in frustration and confusion affecting:
8 / 50
________________ managing the relationship with the seller.
9 / 50
________ is a software engineering task that bridges the gap between system level requirements engineering and software design.
10 / 50
These all are outputs of Initiating Process except
11 / 50
A baseline version __________
12 / 50
The quality of software is said to be high if it meets the
13 / 50
Project Cost Management includes the processes one of them is
14 / 50
Project management processes can be organized into _____________ groups
15 / 50
Decisions also have a--------------------element to them-the “right” decision may not be the "best' decision if it is made too early or too late.
16 / 50
These all are design phase activities except
17 / 50
Each ________ can be subdivided into sub tasks.
18 / 50
________ is path finding________, is path following
19 / 50
The US DOD (1988) defines software quality rather simply as:
20 / 50
Synchronization control helps to ensure that parallel changes performed by two different people do_________.
21 / 50
Project management is a _________of constant communication and negotiation.
22 / 50
The model serves as the basis for the creation of ________ for the Software.
23 / 50
These all are Product Operation Factors except
24 / 50
________ theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins. Select correct option
25 / 50
A Fuzzy user is a related problem.
26 / 50
Cognitive model describes a system as perceived by its _________
27 / 50
are the methods or processes required in total , or in some combination, to achieve the goals
28 / 50
—defining and refining objectives and selecting the best of the alternative courses of action to attain the objectives that the project was undertaken to address
29 / 50
30 / 50
Which of the following might require re-baselining of the cost baseline?
31 / 50
To manage costs for software projects, you need an accurate estimation of costs. To do that, there is a sequence of steps that you need to perform, mark first step in sequence to perform.
32 / 50
Foundational design concepts are.
33 / 50
In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.
34 / 50
During the period of , you will find that software that was produced was generally over budgeted, under scheduled, and of poor quality.
35 / 50
36 / 50
Low motivation is a____ related problem.
37 / 50
Defined scope is a
38 / 50
39 / 50
Predecessor activities need to ________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. Select correct option:
40 / 50
To control versions, you can use _________.
41 / 50
A node on a network schedule is that point in time at which an activity ________.
42 / 50
The British Standards Institution(1986) has stated the quality as
43 / 50
These all are Product Revision Factors except.
44 / 50
All of the following describe the activity list except:
45 / 50
— ensures that appropriate steps to follow the product development procedures are carried out
46 / 50
You can use the Item Traceability Matrix to identify _______ at the end of each phase
47 / 50
Which of the following is a project execution task?
48 / 50
Throughout evaluation and solution synthesis, the analyst's primary focus is on
49 / 50
The model serves as a foundation for software design and as the basis for the creation of _________ for the Software.
50 / 50
What limits the options of the project team?
Your score is
The average score is 0%
Restart quiz