CS615-Midterm
1 / 50
_______is the technical kernel of software engineering
2 / 50
The Introduction of the software requirements specification states the
3 / 50
Efficiency with which a program runs on different platforms or operating systems is Reusability
4 / 50
The US DOD (1988) defines software quality rather simply as:
5 / 50
Most software project manager’s practice a lot of management techniques that are of doubtful authenticity are called
6 / 50
— ensures that appropriate steps to follow the product development procedures are carried out
7 / 50
Which of the following is a project execution task?
8 / 50
Controlling Versions is activity of
9 / 50
10 / 50
is responsible to plan, motivate, organize and control the people who do work on software.
11 / 50
Reviews conducted at each of this phase/s
12 / 50
These all are outputs of Initiating Process except
13 / 50
Tools and techniques of the source selection process include all of the following except
14 / 50
The fourth, and current, phase of software solution began in the early
15 / 50
The model serves as the basis for the creation of ________ for the Software.
16 / 50
—defining and refining objectives and selecting the best of the alternative courses of action to attain the objectives that the project was undertaken to address
17 / 50
During the period of , you will find that software that was produced was generally over budgeted, under scheduled, and of poor quality.
18 / 50
According to the 80/20 rule, 80 percent of the defects arise due to of the process issues.
19 / 50
The quality of software is said to be high if it meets the
20 / 50
Which of the following is a Technology related problem?
21 / 50
Configuration control tools include
22 / 50
includes the processes required to ensure that the project is completed within the approved budget
23 / 50
Software design is actually a multi-step process that focuses on distinct attributes of a program
24 / 50
To control versions, you can use _________.
25 / 50
Software project are carried out sequentially and that each phase is completed before the next is taken up.
26 / 50
Project management processes can be organized into _____________ groups
27 / 50
Mode of specification has a great impact on quality of solution. Forcing SWE to work with incomplete, inconsistence, or misleading specifications result in frustration and confusion affecting:
28 / 50
Each ________ can be subdivided into sub tasks.
29 / 50
In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.
30 / 50
________ is path finding________, is path following
31 / 50
A meeting is conducted at a _________ and attended by both software engineers and customers.
32 / 50
Foundational design concepts are.
33 / 50
The US DOD (1988) defines software quality rather simply as
34 / 50
These all are Product Operation Factors except
35 / 50
Cognitive model describes a system as perceived by its _________
36 / 50
Predecessor activities need to ________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. Select correct option:
37 / 50
What limits the options of the project team?
38 / 50
Defined scope is a
39 / 50
Cognitive model describes a system as perceived by its _________.
40 / 50
A software project that meets all the stated objectives is a success of
41 / 50
________ theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins. Select correct option
42 / 50
The British Standards Institution (1986) has stated the quality as
43 / 50
Synchronization control helps to ensure that parallel changes performed by two different people do .
44 / 50
You can use the Item Traceability Matrix to identify _______ at the end of each phase
45 / 50
includes consideration such as the post-implementation support activities provided to the customer.
46 / 50
The first activity in risk analysis is risk management.
47 / 50
We can classify the problems that affect software projects into categories
48 / 50
________ is a software engineering task that bridges the gap between system level requirements engineering and software design.
49 / 50
A ‘facilitator’ controls the meeting can be _________.
50 / 50
McCall (MCC77 )and his colleagues proposed some software quality factors based on most important aspects of a software product:
Your score is
The average score is 0%
Restart quiz