CS615 Midterm Online Quiz

0%

CS615-Midterm

1 / 50

Each process is described by .

2 / 50

We can classify the problems that affect software projects into categories

3 / 50

The model serves as a foundation for software

4 / 50

Synchronization control helps to ensure that parallel changes performed by two different people do .

5 / 50

Configuration control tools include

6 / 50

A meeting is conducted at a _________ and attended by both software engineers and customers.

7 / 50

Mode of specification has a great impact on quality of solution. Forcing SWE to work with incomplete, inconsistence, or misleading specifications result in frustration and confusion affecting:

8 / 50

________________ managing the relationship with the seller.

9 / 50

________ is a software engineering task that bridges the gap between system level requirements engineering and software design.

10 / 50

These all are outputs of Initiating Process except

11 / 50

A baseline version __________

12 / 50

The quality of software is said to be high if it meets the

13 / 50

Project Cost Management includes the processes one of them is

14 / 50

Project management processes can be organized into _____________ groups

15 / 50

Decisions also have a--------------------element to them-the “right” decision may not be the "best' decision if it is made too early or too late.

16 / 50

These all are design phase activities except

17 / 50

Each ________ can be subdivided into sub tasks.

18 / 50

________ is path finding________, is path following

19 / 50

The US DOD (1988) defines software quality rather simply as:

20 / 50

Synchronization control helps to ensure that parallel changes performed by two different people do_________.

21 / 50

Project management is a _________of constant communication and negotiation.

22 / 50

The model serves as the basis for the creation of ________ for the Software.

23 / 50

These all are Product Operation Factors except

24 / 50

________ theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins. Select correct option

25 / 50

A Fuzzy user is a related problem.

26 / 50

Cognitive model describes a system as perceived by its _________

27 / 50

are the methods or processes required in total , or in some combination, to achieve the goals

28 / 50

—defining and refining objectives and selecting the best of the alternative courses of action to attain the objectives that the project was undertaken to address

29 / 50

These all are outputs of Initiating Process except

30 / 50

Which of the following might require re-baselining of the cost baseline?

31 / 50

To manage costs for software projects, you need an accurate estimation of costs. To do that, there is a sequence of steps that you need to perform, mark first step in sequence to perform.

32 / 50

Foundational design concepts are.

33 / 50

In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.

34 / 50

During the period of , you will find that software that was produced was generally over budgeted, under scheduled, and of poor quality.

35 / 50

These all are design phase activities except

36 / 50

Low motivation is a____ related problem.

37 / 50

Defined scope is a

38 / 50

Synchronization control helps to ensure that parallel changes performed by two different people do .

39 / 50

Predecessor activities need to ________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. Select correct option:

40 / 50

To control versions, you can use _________.

41 / 50

A node on a network schedule is that point in time at which an activity ________.

42 / 50

The British Standards Institution(1986) has stated the quality as

43 / 50

These all are Product Revision Factors except.

44 / 50

All of the following describe the activity list except:

45 / 50

— ensures that appropriate steps to follow the product development procedures are carried out

46 / 50

You can use the Item Traceability Matrix to identify _______ at the end of each phase

47 / 50

Which of the following is a project execution task?

48 / 50

Throughout evaluation and solution synthesis, the analyst's primary focus is on

49 / 50

The model serves as a foundation for software design and as the basis for the creation of _________ for the Software.

50 / 50

What limits the options of the project team?

Your score is

The average score is 0%

0%

Qunoot e Nazilah
Dua e Hajat
4 Qul
6 Kalma
Dua-e-Akasha
Darood Akbar
Surah Fatiha
Dua-e-Ganj Ul Arsh
Dua-e-Jamilah
Ayat-ul-Kursi