CS615 Midterm Online Quiz

0%

CS615-Midterm

1 / 50

Mode of specification has a great impact on quality of solution. Forcing SWE to work with incomplete, inconsistence, or misleading specifications result in frustration and confusion affecting:

2 / 50

Both the software engineer and customer take an active role in software requirements engineering-a set of activities that is often referred to as Requirement:

3 / 50

is an umbrella activity that ensures conformance to standards and procedures throughout the SDLC of a software product.

4 / 50

What limits the options of the project team?

5 / 50

________ is path finding________, is path following

6 / 50

These all are outputs of Initiating Process except

7 / 50

insures that the standards laid down for a preset are followed.

8 / 50

We can classify the problems that affect software projects into categories

9 / 50

These all are Product Operation Factors except

10 / 50

According to the 80/20 rule, 80 percent of the defects arise due to of the process issues.

11 / 50

The Introduction of the software requirements specification states the

12 / 50

identifying and documenting interactivity dependencies

13 / 50

Which of the following is not desirable to become a successful project manager?

14 / 50

Which of the following is a project execution task?

15 / 50

A good system allows you to access relevant information and make informed decisions.

16 / 50

A baseline version __________

17 / 50

Which organization has set the de facto standards for project management techniques?

18 / 50

Thy quality of software is said to be high if it meets the

19 / 50

Using PERT and CPM, ________ , helps you complete a project on time. By using these techniques, you can determine the latest time by when an activity should start to be completed on time.

20 / 50

Each ________ can be subdivided into sub tasks.

21 / 50

McCall (MCC77) and his colleagues proposed some software quality factors based on _________ most important aspects of a software product:

22 / 50

________ identifying which quality standards are relevant to the project and determining how to satisfy them.

23 / 50

Predecessor activities need to ________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. Select correct option:

24 / 50

________ is a software engineering task that bridges the gap between system level requirements engineering and software design.

25 / 50

In problem evaluation area of effort, once problems have been identified, the determines what information is to be produced by the new system and what data will be provided to the system.

26 / 50

Low motivation is a____ related problem.

27 / 50

These all are design phase activities except

28 / 50

These all are outputs of Initiating Process except

29 / 50

These all are Product Revision Factors except

30 / 50

Synchronization control helps to ensure that parallel changes performed by two different people do_________.

31 / 50

Software requirements engineering is a process of all except

32 / 50

To control versions, you can use _________.

33 / 50

These all are Product Revision Factors except.

34 / 50

Decisions also have a--------------------element to them-the “right” decision may not be the "best' decision if it is made too early or too late.

35 / 50

The final activity for a project manager is

36 / 50

Foundational design concepts are.

37 / 50

Software project are carried out sequentially and that each phase is completed before the next is taken up.

38 / 50

Cognitive model describes a system as perceived by its _________.

39 / 50

The British Standards Institution (1986) has stated the quality as

40 / 50

Configuration control tools include

41 / 50

Defined scope is a

42 / 50

McCall (MCC77) and his colleagues proposed some software quality factors based on most important aspects of a software product:

43 / 50

The fourth, and current, phase of software solution began in the early

44 / 50

In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.

45 / 50

— ensures that appropriate steps to follow the product development procedures are carried out

46 / 50

Cognitive model describes a system as perceived by its _________

47 / 50

During the period of , you will find that software that was produced was generally over budgeted, under scheduled, and of poor quality.

48 / 50

includes consideration such as the post-implementation support activities provided to the customer.

49 / 50

McCall (MCC77 )and his colleagues proposed some software quality factors based on most important aspects of a software product:

50 / 50

To ________risks from occurring, the project team prepares the risk plan before the commencement of the project.

Your score is

The average score is 0%

0%

Qunoot e Nazilah
Dua e Hajat
4 Qul
6 Kalma
Dua-e-Akasha
Darood Akbar
Surah Fatiha
Dua-e-Ganj Ul Arsh
Dua-e-Jamilah
Ayat-ul-Kursi